Tag Archives: strawberries (WFPB)

2015/10/09 (F) All Charged Up

We finished the current batch of granola for breakfast and had just finished our meal when Chris, from Bratcher Electric, showed up at 8:45 AM to service the whole house generator.  He let me watch and explained the various steps in the process.  The trickiest part appeared to be replacing the spark plug on the back side of the engine.  Everything else was fairly accessible.  There is a 1/4 turn valve to drain the oil and a rubber tube to get it out to a collection vessel.

Chris had what looked like a small gas can but it was painted blue.  It had a clear plastic tube attached to what would normally be the air vent.  The tube was sized to just fit inside the oil drain hose.  A vacuum pump was threaded on to opening where the pour spout would normally go.  A few pumps of the handle and the device sucked the oil right out of the engine and contained it so he could transport it easily and cleanly.  It was a very clever device, and obviously very handy for someone who does several generator maintenance procedures every day.

He gapped the spark plugs at 0.028″, checked the air filter (it was fine), replaced the oil filter, noting the date on the filter with a permanent marker, and put ~2-1/3 quarts of 5W-30 synthetic oil back in the engine.  He cautioned me to only use the specified filter and pure synthetic oil.  The engine runs hot under load and regular oil can lead to problems.  He checked all of the settings and changed the weekly self-test to run at full speed for the entire time.  He prefers that setting as it gets the engine up to normal operating temperature and helps burn off any moisture in the oil.  He started the unit manually, let it run for a while, and then shut it down and put in back in AUTO mode.

Linda prepared the dry ingredients for her vegan chocolate cupcakes and then put together a grocery list.  She left to go to Meijer’s while Chris was still working.  He finished up around 10:15.  I worked on the bus, using split plastic wire loom to protect the wires that power the fans on the heat exchangers.  I then worked on reconnecting the wires from the front bay electric heater to the supply wires.

A close up view of the fill/bleeder valve assembly for the heat exchangers in the desk bases.

A close up view of the fill/bleeder valve assembly for the heat exchangers in the desk bases.

The supply wires run inside the HVAC duct.  They originally came out of the duct and went through a hole in the floor into the OTR air-conditioning bay and then through the partition wall into the front bay.  I had to cut the cable and pull it through the floor from underneath so I could install the new floor tile.  I could clearly see where the OTR HVAC supply duct came into the distribution duct but when I tried drilling from below I seemed to hit metal.   The bottom of the duct was clearly plywood so I drilled from above with a 1/2″ spade bit.  I got through most of the plywood but again seem to hit metal.  I knew there wasn’t anything in that location, like wires, pipes, or air lines, so I switched to a 1/2″ twist drill and finished the hole.

I dropped a screwdriver through the hole so I could locate it from below.  I then pushed the electrical cable from the heater up through the hole and secured it to a fastener on the forward wall with a cable tie.  Linda got back at this point so I helped get the groceries into the house.  She then mixed a new batch if granola and put it in the oven to bake.  I gathered up my electrical tools, uncapped the feed wires, checked them with a volt meter to make sure they were not energized, connected the feed wires to the load wires, and tucked them back inside the duct.

We had a choice as to what to work on next—fill the heat exchangers and hoses with antifreeze or hang the wallpaper in the hallway—so we had lunch.  Summer has passed, but tofu hotdogs with mustard, onion, and relish, along with some red grapes, was still a tasty lunch.

When we got back to work in the coach we decided to hang the wallpaper.  The pieces were already cut and laid out on the bed.  Hanging them not only got them off the bed, it would allow us to get the wood trim off the bed as well and back on the lower wall.  But not today.  The wallpaper adhesive needs to cure for 24 hours before we work around it and does not achieve its full cure for 5 to 7 days.  We have one piece of wallpaper to hang behind the forward end of the sofa but the wall prep is not finished in that area.  Once that piece is up, and we have the Corian top for the desk, we can complete the installation of the desk and sofa.

Shawna was bringing Madeline at 4:30 PM to spend the night with us.  It was already 2:30 and I needed to get cleaned up and put on non-work clothes before they arrived so we called it a day.  I had once again accumulated quite a few tools in the bus.  I gathered up all of the ones I was done with, returned them to the garage, and locked up the coach.  The UPS truck showed up with my package from B&H Photo which I set aside temporarily while I took a shower and got dressed.

The box looked like it had been treated well in shipment.  I opened the box, carefully removed all of the contents, and compared them to the order/packing list.  Everything was there and appeared to be in pristine condition.  I unwrapped the battery charger and Lithium ion battery, put the battery in the charger, and plugged it in.  The new charger is essentially the same as the one that came with my Sony alpha 100 years ago so I got the old one from the basement.  I bought five additional batteries so I opened one of them and plugged it in to the old charger.  I then found the Instruction Manual and curled up with it on the living room sofa while Juniper (the cat) curled up on me.

The directions with the charger and the batteries indicated that it can take up to 175 minutes to fully recharge a battery and that full charge is not obtained until an hour after the charging light goes out.  So, basically, I need to leave the batteries in the charger for three hours to ensure they are fully charged.  The camera takes one battery, and the vertical grip accessory takes two batteries, so my normal operating configuration will be to have three batteries in the use.  That’s why I have a total of six batteries for this new camera.  I will probably buy another charger so I can charge three batteries simultaneously.

I called Chuck to let him know I got my car back late yesterday but would not be able to move the windshields box until sometime next week.  It turned out that he and Barbara were also busy all weekend.  His daughter, son-in-law, and grandson were in town with more family arriving from Trinidad and Tobago this evening.  Tomorrow is his grandson’s first birthday and Sunday he is being baptized at the church in Ann Arbor where Chuck’s daughter was married.

Shawna showed up just after 4:30 PM.  Madeline had fallen asleep in the car and was slow to wake up, clinging to her mom for quite a while.  Linda brought in the various bags of clothes and toys along with the inflatable bed and got everything situated in the middle bedroom.  When Linda mentioned making cupcakes Madeline finally woke up and became cheerful.  Once her focus was on baking with Grandma Linda Shawna was able to slip away without any drama on Ms. M’s part.

Today was Brendan and Shawna’s friend Jorge’s birthday and the three of them were headed to a new restaurant in Detroit to celebrate.  The restaurant does not take reservations and is apparently very popular at the moment so Shawna was not sure if they would actually get to eat there.

With Linda’s help Madeline mixed the ingredients for the cupcakes and managed to pour most of the batter into the baking tray.  Linda then prepared dinner while I played with Madeline.  We did the ABCs on her placemat, and then colored with crayons.  Dinner was mock chicken tenders, edamame, and steamed carrot rounds with fresh orange segments and sliced strawberries, so it was mostly fresh, whole plant-based foods.

As soon as the cupcakes were cool enough to be frosted Madeline coated each one with the special Halloween orange frosting and the back and orange Halloween sprinkles.  I was summoned to inspect the work and then it was time to eat.  Madeline selected a cupcake for herself and then one for me and one for Linda.  We ate them at the table and they were very good.

After cupcakes we played soccer with two different balls, kicking and throwing them all around the house.  By 8 PM we needed to start winding things down.  Shawna had left her iPad and Madeline selected a Curious George video about Christmas.  Linda and Madeline climbed up in our bed where they could stretch out their legs and watched the first 60% of the cartoon.  I opened two more camera batteries and put them in the chargers and then joined the girls.  We will watch the rest of the cartoon tomorrow morning.

I helped Madeline brush her teeth and Linda got her into her pajamas.  Linda read her several stories and finally got her in bed around 9:15 PM.  During dinner Madeline inquired about having pancakes for breakfast.  (I had made the same inquiry over lunch.)  Linda did not have all of the ingredients she needed so after Madeline went to bed I went to Meijer’s in Howell and bought avocado oil and all-purpose flour.  Linda is trying to use up ingredients rather than stock up on them so I bought a two pound bag of King Arthur organic unbleached enriched all-purpose flour even though I could have bought a 10 pound bag of the Meijer’s brand (bleached and not organic) for only 50 cents more.

Just before going to bed I opened two more batteries and put them in the chargers.  We went to bed at 11 PM but did not turn on the TV to ensure that we did not disturb Madeline’s sleep.  I was basically done with the draft of this post and read some more of the Instruction Manual for my new Sony alpha 99 (SLT-A99V) camera and vertical battery grip (VG-C99AM).  I am really looking forward to using this new equipment but it takes a couple of days to charge batteries, install software, and read manuals enough to be able to configure it for first use.  This class of camera has a lot of adjustable parameters with default settings that may or may not be what any particular user wants.

 

2015/07/04 (S) Another Fourth

Linda was up at 7 AM and grabbed a shower as Madeline is usually awake by 7:15 and up between 7:30 and 7:45.  Madeline tends to wake up hungry so Linda likes to have breakfast ready to go.  I was up by 7:20 and also grabbed a quick shower.  When Madeline was finally ready to get up she let Grandma Linda carry her into the living room and hold her in her arms for a while.  When she was ready to sit up Linda brushed her hair and then Madeline returned the brush to the master bathroom.  Linda got her changed into her day clothes and then we all had breakfast.  Linda and I had our usual coffee, orange juice, and granola with fresh berries plus some vegan sausage links.  Madeline also had the sausage links and berries but her main course was toaster waffles with a little bit of real maple syrup.  Yum.

One of the swans at the Brighton Mill Pond.

One of the swans at the Brighton Mill Pond.

After breakfast Madeline wanted to go look for chickens so she and Grandma Linda went for a walk.  When they got back I learned that they saw three chickens, a duck, some bunnies, and a chipmunk (ground squirrel).  We then read a couple of stories and built a fort in the living room.  We talked about going to the Mill Pond in Brighton to see/feed the ducks but there was some sort of running event this morning, a parade at 10 AM, and then a rubber ducky race at the Mill Pond following the parade.  It is the 4th of July, after all, and most communities have celebratory events going on all day and into the evening, ending with fireworks displays.  That sounded like a crowd to me, with the attendant parking hassle, but we figured the crowd might have thinned sufficiently by 10:30 AM to make the experience a good one and decided to chance a visit.  Linda made PB&J sandwiches and packed some grapes and cookies.

Madeline sitting at a picnic table at the Brighton Mill Pond playscape.

Madeline sitting at a picnic table at the Brighton Mill Pond playscape.

We parked in the lot behind the La Marsa restaurant, which is far away from the Main Street part of the Mill Pond, and walked down the boardwalk to the playscape.  There were a lot of people gathered around the Pond for the rubber ducky race and quite a few children at the playscape with their adult chaperones.  Madeline explored the entire playscape with great enthusiasm.  By the time she was done it was 11:30 AM and she was hungry so we had lunch at one of the picnic tables under the shade of a big tree.

After lunch Grandma Linda stood in line with Madeline to use the bathroom.  We then walked around the Mill Pond and paused to cover our ears while the emergency sirens were tested, this bring the first Saturday of the month.  We had a leisurely stroll back to the car and I had a nice chat with a fellow photographer along the way.  He is a local artist/writer with a deep interest in the Mill Pond and the wildlife that calls it home.  He wrote down his website URL for me: http://Words4It.com.  I checked it out when we got home and it is a valuable resource for anyone interested in the flora and fauna of the Brighton Mill Pond.

The various shades of green with a few orange flowers caught my eye while strolling the boardwalk at the Brighton Mill Pond.

The various shades of green with a few orange flowers caught my eye while strolling the boardwalk at the Brighton Mill Pond.

Back at the house Madeline had some soy yogurt and fresh berries before taking her nap.  I don’t know if she fell asleep and woke up or never completely fell asleep but around 2 PM I heard her fussing.  When I checked on her she said she needed to go to the bathroom.  Linda had fallen asleep but that is a duty she takes care of so I woke her up.  Madeline took care of her business, laid back down, and fell asleep.  Linda stayed awake.

With Madeline asleep I took the opportunity to go to my office and check e-mail.  There was one from Scott at QTH.com indicating that the SLAARC website had been copied to the QTH web servers and was ready for testing.  I think that meant the GoDaddy DNS had been changed to point to the QTH installation but I don’t think the domain name registration had been moved yet.  I will need to clarify that with Scott on Monday.  I also had an e-mail from Gary at Bus Conversion Magazine with the draft of the June 2015 issue attached.  This issue has part 3 of my 4-part article on the 2011-12 exterior renovation of our Prevost H3-40 motorcoach.  I replied that I would proofread it and submit corrections before I go to bed tomorrow night.

Madeline takes the high road and Linda takes the low road on the Brighton Mill Pond boardwalk.

Madeline takes the high road and Linda takes the low road on the Brighton Mill Pond boardwalk.

Although Linda is much more physically active with Madeline than I am I was feeling the need for a nap and laid down at 3 PM.  I heard Madeline get up around 4 PM and I finally got up at 4:15.  Linda enlisted Madeline’s help preparing dinner while I took pictures.  The first task was shucking the whole ears of corn.  Next, Linda let her put them in a large pot of water, add a little bit of sugar, and stir.  While the pot started to heat up on the stove Madeline helped prepare the strawberries by washing them.  Linda then got the vegan burgers ready to grill (inside on our stove top griddle) and prepared the garnishes.  Madeline does not get to help with things that are sharp or hot.  Soon enough it was time for dinner and we all enjoyed our corn-on-the-cob and vegan cheeseburgers. For dessert we had some more of the chocolate cake that we made yesterday with fresh strawberries.

We spotted this young bunny along the boardwalk at the Brighton Mill Pond.

We spotted this young bunny along the boardwalk at the Brighton Mill Pond.

After dinner I cleaned up the dishes and we went out on the deck to sit in the chairs and enjoy a near perfect Michigan summer evening while we watched the bunnies eating grass.  Around 7:15 PM we watched another Sesame Workshop DVD.  This one was on Shapes and Colors.  It was over by 8 PM and Madeline started getting ready for bed which was a very jovial affair.  First the potty, then jammies, then tooth brushing followed by finding blankies, “bebes” (pacifiers), and stuffed animals, all the while laughing and giggling.  Linda finally got her to sit quietly and read her a story which calmed her down enough to go to bed.  If her thoughts drift to her mommy and daddy she will get weepy—it’s part of being two and a half—but we have been successful on this visit keeping her engaged enough to avoid anything more than some occasional brief tears.

Madeline washes the strawberries.

Madeline washes the strawberries.

We split the remainder of a bottle of Leelanau Cellars Winter White wine we had opened some time ago but had vacuum sealed and it was still fine.  Linda finished the dishes and loaded the dishwasher while I filled in the day’s details on this blog post.  Both cats came out of hiding and sought our attention.

We have been hearing fireworks, and/or gunfire, for many weeks now and today was no exception.  Two nights ago someone in the neighborhood was firing off, or shooting, something until well after midnight.  There were more fireworks tonight, as expected, and the activity intensified after 9 PM as dusk gave way to night.  The cats were not completely relaxed about the noise but seemed to tolerate it.  As far as we know Madeline slept through all of it as she is a very sound sleeper.

 

2014/09/15 (M) Congratulations, You Have Gas

As I reported in the blog post for this past Saturday a natural gas hookup crew was at our house in the early morning but it was the wrong crew (trench/plow) installing the wrong size gas line (1/2″ id).  The correct crew (directional boring) showed up today around 9 AM and started boring the line for our neighbor’s yard across the street.  I chatted with the crew briefly and they said we were next.  They had placed a large role of the proper size gas line (1″ id) in our yard, so I knew they knew what they were doing.

Ed, who had stopped by on Friday and runs the hookup crew, was not sure whether they would hang the meter and connect the line at both ends today, but if not, tomorrow for sure.  Their presence on site, however, meant that I would need to be in contact with three contractors fairly soon to follow up on arrangements to get them out here ASAP, and in the following order:

  • DCM Heating and Cooling, to disconnect the propane from the house and tie the new 2″ black iron pipe together with the pipe into the house and connect them to the consumer side of the gas meter.  Also, to start up the new library and garage furnaces.
  • TOMTEK HVAC to convert the hot water base-board heating system to natural gas.  Tom was going to check today with Weil-McLain on the parts needed for the conversion and let me know.  Our own research suggested that a natural gas orifice plate was the only part needed, but a number of steps were involved in the installation and I doubt that W-M would sell me the part directly.  (I did find it later online for $31 plus S&H, so I could buy it if I wanted to.)
  • Bratcher Electric; to convert the whole house generator, do the annual maintenance, and run the new service entrance cable for the garage panel.

Mike Bratcher was here a month ago to look at the job but had not gotten a price to us yet for the work.  They have been slammed with repair jobs as a result of late summer storms.  The generator is the least critical component at the moment as it is on its own propane tank, but we want to get it switched in a timely fashion so we can call AmeriGas and have both tanks removed at the same time.

(Ed told me later in the day that Consumer’s Energy requires us to be switched over to natural gas within 30 days of having gas to our meter.  He also said that a recent Michigan law (last year) made it illegal to have multiple fuel sources to a house.  Since the generator is on its own propane tank and that tank is not connected to, or provide propane to, the house or anything in the house, technically we would not have two different fuels going to the house even if we left it hooked up.  Still, we are not looking to create a “situation” with Consumer’s Energy.  Presumably the multi-fuel prohibition does not include electricity and wood.)

Keith showed up around 9 AM to cut the grass.  I chatted with him briefly about cutting the new grass, which had gotten long enough in many spots that I thought it was probably time for the first cutting.  I picked up some small tree branches that were scattered about the yard from recent storms, and warned him about the trench at the southeast corner of the house.  I chatted with him some more as he was finishing up with the string trimmer.  He said the grass was “April grass, not September grass.”  The grass itself (internally) was very moist, not just the soil.

This is how Keith cuts over 4 acres of grass in a few hours.

This is how Keith cuts over 4 acres of grass in a few hours.

Linda had reserved Doc Martin, Season 5, at the Howell Library and had an e-mail that it was available and needed to be picked up by the end of today or we would go to the end of the waiting list.  She needed to be at the bakery by 11 AM so she left around 9:45 AM to be at the library when it opened at 10 AM.  I would have gone to get it but I was “stuck” at the house as long as contractors were, or might be, working here.  I also needed to be here to pay Keith when he finished cutting the grass.

Linda met with the folks at the bakery (where she was the Controller and Treasurer for the 10 years before she retired) on Friday regarding a major software conversion project that she is going to do for them and was finally feeling like we could afford a new range.  She is a very good accountant/CPA and has always worked hard for what she earned, but has always been reluctant to spend money.  We grew up in very different circumstances and that reluctance on her part has provided a good balance over the years as I tend to be less concerned about what things cost and more focused on making sure we have what we need and are getting good functionality and quality for what we spend.  One component of my formal education and work experience was engineering, and that developed a certain way of thinking about things that has stayed with me ever since.  Need is, of course, relative.

We had been deferring a decision about the new kitchen range but decided on Friday evening that, with the natural gas hookup imminent, we would get a new one rather than convert our old one.  We decided on the model we wanted, a G.E. JGB870DEFWW, and knew the price, delivery time, and installation charge from Lowe’s.  I also talked to Curt at D. R. Appliance, a local family owned appliance store, on Saturday and expected to hear back from him today with pricing and availability.  That call came late morning and their price, while a little higher than Lowe’s, was close enough to be worth the possible end-of-week delivery and installation so I told them to go ahead and order it.

By 3:30 PM the gas line to our house was in the ground and the meter was mounted on the side of the house but a crew was still digging out by the street trying to clear access to the main line so the fuser could tie our line and our neighbor’s line into the 2” main line.  My camera battery went dead while they were installing the meter so I grabbed a few shots on my cell phone while the camera battery recharged.  Linda got home around this time and got to see some of the final steps in the process.

I followed the process closely all day and tried to get photos of most of the details, especially as they hung the meter, tied the line in, and pressure tested it.  All was good, so they tapped the main line and we finally had gas in our branch line.  They purged the line, reconnected it to the meter inlet, tested the meter and connections for leaks, and then verified gas availability to the outlet connection.  At 5:30 PM they plugged the outlet, put the hang tags on, and handed me the door knocker tag that said “Congratulations, you have gas.”

We always seem to have interesting things in our yard.

We always seem to have interesting things in our yard.

Linda took a call from Bob at Country Squire Fireplace and Lighting regarding our quick disconnect for the Broil King outdoor grill.  She indicated that I was busy with the gas crew and would call them back tomorrow.

Late last week we received an invitation to a political fund-raiser for Brian Robb, an incumbent councilman in Ypsilanti, Michigan.  We do not live or vote there, but Brian is Kate de Fuccio’s significant other, and Kate is a former co-worker of mine and continues to be a very good friend of ours.  I called DCM Heating & Cooling and left a message for Darryll that we had gas to the meter.  We left around 6 PM and arrived at the Tower Inn Cafe around 7 PM.  We made a donation to Brian’s campaign and Kate ordered a small vegan pizza for us.  We visited for about an hour and then took our leave.

When we got home we relaxed in the living room thinking about how nice it will be to have our natural gas fire logs while we had some fresh strawberries and nectarines for dessert.  I also had a mug of hot apple cider which put me in the mood to go to bed.

 

2014/09/10 (W) A Functioning Landline

The Ibuprofen/Tylenol mix did the trick and I slept comfortably through the night.  Twinges were just starting as we were waking up, so breakfast was two zucchini muffins, half of a banana, and 800 mg of Ibuprofen, washed down with orange/grapefruit juice.  Linda went for a walk after breakfast as it was supposed to be rainy most of the day.

I spent part of the morning selecting and re-sizing photographs from the Arcadia Bus Rally 2014, uploaded them to a folder in our Dropbox, and e-mailed the link to Brenda Phelan who runs the rally with her husband Bill.  She had put out a request on Facebook for photos if anyone had them.  I did an article for Bus Conversions Magazine on that rally shot over 700 photos, so yeah, I had a few.

I registered us for an RVillage Ambassador webinar later today on the new mobile app, and then came upstairs to have lunch.  We enjoyed the vegan Sloppy Joe’s Linda had made, along with some vegan baked beans (canned) and store bought apple sauce.  It had been raining lightly for a while and the intensity increased while we ate, but it fell straight down with little to no wind.  The radar loop on Wundermap (Weather Underground) showed that we were in the leading edge of a large fetch of moisture that would likely train over our location for several hours and that is, in fact, what happened.

I took a short nap.  I rarely do that, but I always enjoy it when I do.  I worked the rest of the afternoon at my computer editing blog posts and finally getting around to selecting and processing photos to go with some of them.  I had called Kerry Fear this morning regarding snowplowing this winter and he stopped by the house around 3:45 PM to meet with us.  He lives nearby and plows our neighbor’s driveway, which is how we got his name.  We agreed to hire him for the season on a handshake; no contract or pre-payment.  He will send us a bill every now and then and we will pay it.

Linda made creamed corn for dinner and served it alongside vegan Sloppy Joe sandwiches and fresh strawberries.  Again, a soft, easy on the teeth, meal that was very tasty.

The RVillage webinar started at 7 PM EDT and lasted 45 minutes.  They wanted feedback on this latest development by Friday so they can finalize it for general release.  I continued working on photographs for the blog and installed a set of updates on our Linux box before calling it quits for the evening.  Linda had started watching the first episode of Sherlock from last year so I watched most of it with her.  Much to our disappointment Doc Martin has disappeared from Amazon Instant Video as part of our Amazon Prime account.  We can still get it, but we would now have to pay extra.  As much as we like the series we are not going to pay extra to watch it.

It spite of the rain today, we made and received a number of phone calls on our AT&T landline and were online through our DSL connection quite a bit, including streaming the episode of Sherlock, all without noise or service interruptions to the best of our knowledge.  We are hopeful that our AT&T service is finally restored and will continue to operate reliably.

One of the calls was from Chuck letting me know that Matt at Bob’s Speedometer Service had tested his VDO bus speedometer and found it to be broken and not repairable.  Chuck ordered a new one through Matt, who will take care of programming the odometer with the current mileage.  Once it comes in and Chuck verifies that it works I will likely be ordering one for our bus since ours has failed in the same way as Chuck’s.  I could go ahead and remove ours and take it in, but I have lots of other things to work on a figured it made sense to wait and see how this works out for Chuck.

 

2014/08/11 (M) SLAARC/WordPress

Some of the members of SLAARC are former Detroit Edison employees (now DTE Energy) and one of them (Bruce, W8RA) currently works for Intercontinental Transmission Company (ITC).  Bruce was curious what size transformer we had and said that there were likely numbers on it that I could read with a pair of binoculars.  I went out this morning to check, but the only info on the transformer can is a metal plate that is too small and illegible to read from the ground even with our fairly good binoculars.

Darryll (DCM Heating & Cooling) had not shown up or called by 10:30 AM.  His work doesn’t make a mess of our yard or house, at least it hasn’t yet, so it is less of a concern that he is not here working today than it was with the landscaping.  When he left Thursday he had a short list of parts he needed to get and perhaps could not do that until this morning.  Or he may have gotten emergency service requests, which take priority over new installations.  Still, we would like to have the new HVAC work completed in the next week or so to make sure it is done ahead of the natural gas hookup.

As part of that work I have to complete some of the electrical pieces, finish dry-walling the utility closet, and continue cleaning, repairing, and organizing the garage while we have the storage pod.  I then need to get to work on a long list of bus projects.  I also have a lot of desk/computer work to do and I prefer to do that when I know I can settle in for a long stretch.  I tend not to be in the right frame of mind for desk work when I do not know if/when contractors are going to show up.  It’s turned out to be a busy, and in some ways complicated, summer that way.  Darryll called late morning to say they would be back first thing Wednesday morning.  That information allowed me to adjust my expectations and settle in for a long day and evening at my computer.

My main focus was working on the page content for the new SLAARC WordPress website, which occupied me until dinnertime with some e-mail mixed in.  After dinner I started uploading blog posts beginning with the one for July 7th.  I decided that I would not select and upload photos for most of the posts in July and early August and instead create more extensive gallery posts for the landscaping work and the garage/HVAC project.

One of the things I have noticed in the past week is that our Internet connection seems to be faster, or at least my e-mail processes much quicker than it used to.  That could be the result of the AT&T repair on the 4th, which ended up moving us to entirely new wire pairs, or a change that AT&T made to our DSL service back on the 3rd (when it kept going off temporarily), or it could be that QTH upgraded their e-mail server system, or some combination of these.  Whatever the case, it seems to be an improvement.

Phil from Precision Grading called at noon to see if he could stop by sometime after 3 PM today.  It was raining gently at the time but when he called back a little after 3 PM the rain had finally opened up into a sustained downpour.  He had an 8 AM appointment in Hell (Michigan) and we agreed that tomorrow morning after his appointment would probably be a much better time for him to stop by.

We ordered a “cat tent” the other day and it showed up this afternoon.  We opened it and set up in the living room with the “door” tied open so the cats could explore the inside.  They were wary, but did go in briefly.  It’s kind of like a back-packing tent but all the fabric, including the floor, is mesh.  We thought the floor would be a solid material, but it’s not.  It will be OK for use on our deck at home, but seems less suitable for use on the ground when we are RVing.  We intended to use it for both so we are not sure if we are going to keep it.

For dinner Linda made a tomato-onion-mushroom ragu and served it over a three rice blend with a dark mixed greens salad on the side.  Later she served fresh strawberries with Lotus brand cookies and dark chocolate with bits of almond and sea salt.  Seriously, what’s not to like about that?

 

2014/07/27 (N) Attic Access

We had a long day of work today.  We were up just after 7 AM, had a light breakfast of toast, fruit juice, and coffee, read a few blog posts, and got to work.  My first task was to apply a second, light coat of drywall compound to all of the divots in the wall.

Our main morning task was the installation of the fold-down ladder for the garage attic.  It was definitely a two-person job.  Per the instructions, we installed temporary installation boards to support the assembly while we secured it in place.  The installation required one of us to be in the attic and that job fell to me.  We put the assembly on top of a plastic shelving unit to get it close to the ceiling.  Once I was in the attic with all of the tools I would need, including a headlamp, Linda slid the shelving unit so the assembly was directly under the rough opening.  It was still too far from the ceiling for me to reach from above so she placed two footstools under it.  I was then able to reach one end from above and pull it up into the opening while she lifted the other end into position from below.

We read and followed the directions carefully so we already had the pull string and T-handle installed.  That allowed Linda to move the plastic shelves out of the way, carefully open the door from below, and position the step ladder.  I dropped her the cord for the worklight and then had enough light to work comfortably.  We temporarily secured the unit with deck screws.  They were cheap screws and the heads tended to strip easily, but we got them in far enough to hold the unit in place while I installed the lag screws.

The 10 lag screws got installed through pre-drilled holes, six of which went through metal hinge plates.  The instructions said to drill through these holes into the trusses and headers, but the folding ladder hardware made that difficult, and my drill buts were all a bit short to do much.  By cutting the zip ties and partially unfolding the ladder I was able to get all 10 lag screws most of the way in with my drill.  They all had to be shimmed.  The final tightening was done with a socket and ratchet.

We took a break for lunch around 1 PM and had leftover miso soup, tofu hot dogs, and fresh apples.  I made a quick run to Lowe’s to get some additional electrical parts I needed to install lights and a light switch in the garage attic.  While I was there I also bought a baby gate for our basement stairs.  Up until now we have blocked the landing for the basement stairs with a couple of chairs when grand-daughter Madeline has come to visit.  Now that she has successfully spent the night at our house we anticipate many more such visits and wanted a more permanent solution.

The device I bought had a gate with a latch.  It was designed to be installed under tension, but the directions said it had to be anchored to the walls if used at the top of a flight of stairs.  We were not thrilled about mounting it to the walls, but we did.  The installation took about an hour to complete.

Back in the garage I found an old, unopened drywall sanding/finishing sponge.  It had a 1/4″ thick coarse pad on one side for sanding.  The regular sponge side was used to wipe off the drywall and slightly wet the areas to be sanded.  I let the sanded areas dry, wiped everything down, and applied a coat of white exterior semi-gloss to the area of the two existing walls and the ceiling that will be inside the utility closet.

The probability of rain rose steadily though the day and finally resulted in thunderstorms around 4:30 PM.  Steve said yesterday he would be here today and I tried to get him to understand that based on the forecast he needed to be here early.  He wasn’t.  He showed up with the excavator about an hour after the rains, by which point the retaining wall work site had turned to mud.

He took the excavator back there anyway and we watched him work while we had dinner, which consisted of a very nice green salad with strawberries and the rest of the Pad Thai from last night.  (Even left over it was still exceptional.)  He was moving boulders and a lot of dirt trying to get rid of the small mountain range that blocked the flow of water away from our lower deck and was spreading the dirt around in an effort to create some of the final grading.  He brought a helper with him and they had long lengths of drain pipe that I think the intended to install.  But the skies darkened, the rain started, the wind came up, and the warning sirens came on.  He shut off the machine and the two of them made a run for their truck and left.  More rain is forecast for tonight with a chance of thunderstorms, possibly severe.  The probability for rain on Tuesday is currently 60%, and stays at 40% through Wednesday.  At this juncture it appears that they won’t get much work done here this week, and their machine may be stuck here until it dries out.

After dinner Linda and I finally built the base for the platform where the library HVAC unit will be installed.  It’s a 40″ deep x 46″ wide box with center cross bracing.  It’s made of pieces of 2 x 12 on edge.  We set it in the northeast corner of the garage, leveled it with shims, and secured it to the studs in the walls with 3.5″ nails.  I had to make all of the cuts with my Rockwell 8″ circular saw as the chop saw won’t cut something that wide.  I did not cut the plywood platform as I need to install it after the new (west) wall of the utility closet is in place so I can nail through the base into the wall studs.  I will, however, cut the plywood tomorrow before the wall is built as I will be able to set it on the base and trace around it on the underside to get a perfect fit.

My goal for tomorrow is to cut the platform, build the west wall, set it in place and anchor it, and install the platform.  Linda has a 12:30 PM dentist appointment, so I will have to do most of this work by myself.  By that point I will need to get cleaned up, shift gears, and get ready for a 4 PM FMCA Education Committee work session.