[ There are 19 photos in this post. ]
MONDAY 23 January
I
did not expect work to be done on Sunday, and none was. I also did not know when a crew would be out next to continue the project, but I did not have to wait long to find out. Around 9:30 AM, a three-person crew showed up from Motor City Electric Utilities, a DTE contractor. They arrived with a crane/auger truck and a bucket truck, but they also had a trailer with a small excavator (back-hoe) with a 12” bucket.
The first thing then did was start hand digging (with a shovel, obviously) by the old pole, looking for the underground service conductors from the house. The AT&T line to our house (no longer in service) also runs underground, along the same/parallel path as the power lines. (The service conductors for the house run underground from the meter, at the SW corner of the garage, to the old pole and then up to the transformer. I presumed these were one continuous run, but splices were eventually found underground at the base of the old pole.)
The next thing they did was open the disconnect switch so they could work safely around the conductors from the transformer secondary taps to the house. But first they worked on disconnecting the AT&T and Comcast cables from the old utility pole, raising them up, and securing them to the new pole. As part of this work, they had to route the existing AT&T cable down the new pole as best they could. (The Comcast/Xfinity cable comes to our house from a different pole in the SE corner of our yard.)
At this point, the existing house underground service conductors were disconnected from the new transformer and the old pole, and cut off about 4’ above where they exited the ground. The AT&T cable was also disconnected from the old pole, but not cut. (Note that our Comcast/Xfinity cable comes to our house from a different pole in the SE corner of our property.) With everything disconnected from the old pole, the crane truck was then used to pull it out of the ground then lay it down. It was then lifted and put on a pair of racks on the crane truck to be taken away. The hole left by the old pole was partially filled in, but was reused to install the new ground pedestal (junction box).
The crew had decided early on that they were going to install the new ground pedestal (junction box) in the hole left by the old pole. At this point, they dug up the underground service conductors from the house for a few feet back from the pedestal location. A new cable assembly, consisting of three (3) 350 kcmil conductors, was then routed down the new pole to provide the service drop to the pedestal. (At 350 thousand circular mils, these are big multi-strand conductors.)
At the upper end, the three wires were joined to the secondary transformer wires at the rack. The bottom end was left loose initially. The support post for the pedestal was then set into the ground and the conductors from the pole and the house positioned so the bottom pedestal cover could be attached. The two sets of wires were then spliced together using very large, insulated terminal blocks for the hots and an uninsulated junction block for the neutrals. The upper cover was put in place and secured, and all areas that were still excavated were filled back in.
Last, but not least, the disconnect switch was closed and utility power was restored to the house. I e-mailed our planning consultant and included photos of the ending status of the work.
Although the crew was done working on the DTE-related project of getting power to our barn, they were not done working at our property. The repositioned their equipment near the SE corner of our property and proceeded to grab one of the new 45’ utility poles from the ditch down the street and drag up to our place. They had a work order for this pole as well, and used their crane truck to pick it up and deposit it in our yard. They then spent a bit of time looking at the pole they had to replace. In the end, they left without doing anything else, but I don’t know why. Perhaps they did not have everything they needed, or it was just too late in the day to start. It looked like a tricky job to me, as power, phone and broadband lines T off at this pole and go across the street to the pole that supplies our neighbor’s house.
As always, I e-mailed our DTE planning consultant and included a few photos of the work.
…